Sarkari RiseLogin

Time And Work Questions for SSC GD

Free, AI-curated practice for the Time And Work section of SSC GD. We have 41+ verified questions in this bank. Below: 5 sample questions. Sign up free to unlock unlimited practice + AI explanations + per-topic analytics.

▶ Start free — SSC GD mockAll SSC GD resourcesAlready a user? Sign in →
Why this topic matters · 7 min read
Time and Work is a high-frequency topic in SSC GD (appears in 2-3 questions per paper). Tests your ability to calculate work rates, combined work, and time taken by workers. Expect direct application questions, pipe-cistern variants, and work-sharing scenarios. Weightage: Medium-High. Key skill: converting 'work done' into rates and solving via equations.

Core Concept: Work Rate

Work is a job to be completed. Rate is how much work one person/machine does per unit time. If a person completes a job in 10 days, their rate is 1/10 of the job per day. This fraction (1/time) is the KEY to all time-and-work problems. Always think in terms of 'fraction of work per day', not absolute numbers.

  • Work Rate = 1 / Time taken (if working alone)
  • If A completes work in 10 days, A's rate = 1/10 per day
  • If B completes work in 15 days, B's rate = 1/15 per day
  • Combined rate = Sum of individual rates
  • Time taken together = 1 / Combined rate
Key formulas
Individual Rate
Rate = 1/T (where T = time to complete work alone)
When: When you know how long one person takes to finish the job
Combined Rate
Combined Rate = 1/T_A + 1/T_B + 1/T_C + ...
When: When multiple workers work together on the same job
Time Together
Time = 1 / Combined Rate
When: To find how long it takes all workers together to finish
Work Done in Time t
Work = Rate × Time
When: To calculate portion of work completed in a given period
Worked examples

A finishes a job in 12 days. B finishes the same job in 18 days. How long if both work together? Rate_A = 1/12, Rate_B = 1/18. Combined = 1/12 + 1/18 = 3/36 + 2/36 = 5/36. Time = 36/5 = 7.2 days.

A does 1/5 of work in 2 days. How long to finish alone? If 1/5 takes 2 days, full work takes 2 × 5 = 10 days. Rate = 1/10 per day.

Two-Person Work Problems

Most SSC GD questions involve two workers with different rates. The trick is to set up the rate equation and solve. Common scenario: A and B work together for some days, then one leaves, the other finishes. Break the problem into phases and use Work = Rate × Time for each phase.

  • Always convert 'days to complete' into daily rate (fraction)
  • If A and B work together for x days, work done = (1/T_A + 1/T_B) × x
  • If A works alone for y days after B leaves, work done = (1/T_A) × y
  • Total work = 1 (always, unless stated otherwise)
  • Set up equation: Phase1_work + Phase2_work + ... = 1
Worked examples

A finishes work in 20 days, B in 30 days. They work together for 5 days, then B leaves. How long does A take to finish? Together rate = 1/20 + 1/30 = 5/60 = 1/12. Work in 5 days = 5/12. Remaining = 7/12. A's time = (7/12) / (1/20) = (7/12) × 20 = 140/12 = 11.67 days.

A and B together finish in 10 days. A alone in 15 days. B alone in? Combined rate = 1/10. A's rate = 1/15. B's rate = 1/10 - 1/15 = 3/30 - 2/30 = 1/30. B takes 30 days.

Efficiency and Work Ratio

Efficiency is another word for work rate. If A is twice as efficient as B, A does twice the work in the same time, or same work in half the time. Efficiency ratio directly translates to rate ratio. This is useful when the problem gives relative efficiencies instead of absolute times.

  • Efficiency ratio = Inverse of time ratio
  • If A takes 10 days and B takes 20 days, efficiency ratio A:B = 20:10 = 2:1
  • If A is 3 times more efficient than B, A takes 1/3 the time B takes
  • When work is divided by efficiency, each person gets work proportional to their rate
  • Payment or work share is usually proportional to efficiency
Worked examples

A and B's efficiency ratio is 3:2. They complete work in 12 days together. How long for A alone? Combined rate = 3+2 = 5 parts. A's share = 3/5. B's share = 2/5. If combined takes 12 days, A alone takes 12 × 5/3 = 20 days.

A is twice as efficient as B. Together they finish in 8 days. A alone? If B takes time T, A takes T/2. Combined rate = 1/(T/2) + 1/T = 2/T + 1/T = 3/T = 1/8. So T = 24. A takes 12 days.

Pipe and Cistern (Water Tank) Problems

Pipes filling/emptying tanks follow the same rate logic as work problems. Inlet pipes add water (positive rate), outlet pipes remove water (negative rate). Net rate = Inlets - Outlets. Time to fill = 1 / Net rate. This is a common SSC GD variant.

  • Inlet pipe rate = 1 / Time to fill tank alone (positive)
  • Outlet pipe rate = 1 / Time to empty tank alone (negative)
  • Net rate = Sum of inlet rates - Sum of outlet rates
  • If net rate is positive, tank fills; if negative, tank empties
  • Time to fill/empty = 1 / |Net rate|
Worked examples

Pipe A fills tank in 6 hours, Pipe B empties in 9 hours. Both open together. Time to fill? Rate_A = 1/6 (positive), Rate_B = -1/9 (negative). Net = 1/6 - 1/9 = 3/18 - 2/18 = 1/18. Time = 18 hours.

Pipe A fills in 10 hours, Pipe B fills in 15 hours, Pipe C empties in 20 hours. All open. Time to fill? Net = 1/10 + 1/15 - 1/20 = 6/60 + 4/60 - 3/60 = 7/60. Time = 60/7 ≈ 8.57 hours.

Work Done by Multiple Workers Over Different Periods

Advanced scenario: A works for x days, B works for y days, C works for z days (possibly overlapping or sequential). Calculate work done in each period separately, sum them, and set equal to 1 (or given total work). This requires careful tracking of who works when.

  • Break problem into time phases (when worker composition changes)
  • For each phase, calculate: Work = (Sum of rates in that phase) × Duration
  • Sum all phases' work and equate to total work (usually 1)
  • Solve for the unknown (usually time or rate)
Worked examples

A and B work together for 4 days. Then A leaves, B works alone for 6 days. A finishes in 12 days, B in 18 days. Check if work is complete. Phase 1: (1/12 + 1/18) × 4 = 5/36 × 4 = 20/36 = 5/9. Phase 2: (1/18) × 6 = 6/18 = 1/3 = 3/9. Total = 5/9 + 3/9 = 8/9. Not complete; 1/9 work remains.

A, B, C work together for 2 days, then A leaves. B and C work for 3 days. A does work in 10 days, B in 15 days, C in 20 days. Work done? Phase 1: (1/10 + 1/15 + 1/20) × 2. LCM(10,15,20)=60. = (6/60 + 4/60 + 3/60) × 2 = 13/60 × 2 = 26/60. Phase 2: (1/15 + 1/20) × 3 = (4/60 + 3/60) × 3 = 7/60 × 3 = 21/60. Total = 26/60 + 21/60 = 47/60.

⚠ Common mistakes to avoid
  • Confusing time with rate. If A takes 10 days, rate is 1/10 per day, NOT 10. Aspirants often use 10 directly and get wrong answers.
  • Forgetting to convert to common denominator when adding fractions. 1/12 + 1/18 requires LCM(12,18)=36, not just adding numerators.
  • In pipe problems, forgetting to assign negative sign to outlet pipes. Outlet rate should be subtracted, not added.
  • Setting up the equation wrong when work is divided into phases. Always track which workers are active in which phase.
  • Assuming all work = 1. Some problems state work in units (e.g., 100 units). Read carefully and adjust the equation accordingly.
  • Misinterpreting 'A is twice as efficient as B'. This means A's rate is 2x B's rate, so A takes half the time, NOT double.
🧠 Memory aids
  • RATE = 1/TIME. This is the golden rule. Every time-and-work problem starts here. Memorize this fraction inversion.
  • COMBINED = SUM OF RATES. When workers team up, add their individual rates. Simple addition of fractions.
  • WORK = RATE × TIME. The universal formula. Use it in every phase of a multi-phase problem.
  • INLET POSITIVE, OUTLET NEGATIVE. In pipe problems, inlets add (positive), outlets subtract (negative). Think: filling vs draining.
  • EFFICIENCY RATIO = INVERSE TIME RATIO. If A:B time is 2:3, then A:B efficiency is 3:2. Flip the ratio.
🎯 SSC GD exam tips
  • SSC GD typically asks 2-3 time-and-work questions per paper. Expect straightforward two-person problems (A and B type) and one pipe-cistern variant. Rarely asks complex three-person scenarios.
  • Time limit is tight (15 seconds per question in Tier-1). Pre-calculate common LCMs (12, 15, 18, 20, 24) to save time. Avoid long decimal calculations; stick to fractions.
  • Recent papers show preference for 'work done in x days' followed by 'remaining work done by one person' structure. Practice this pattern repeatedly.
  • Pipe problems in SSC GD are usually straightforward (2-3 pipes max). Outlet pipes are common; watch for 'leak' or 'drain' keywords.
  • If a problem mentions 'efficiency' or 'work ratio', convert to time equivalents immediately. Don't try to solve in efficiency units; it confuses.
  • Always verify your answer: plug back into the original problem. If A takes 20 days and B takes 30 days, together should be less than 20 days (usually 12 days). Sanity check saves marks.

Sample questions

Q1 · medium · PYQ 2023
A and B can do a job in 16 days and 12 days respectively. 4 days before finishing the job, A leaves B. B has started the work alone. Find how many days B has worked alone.
  1. 6 days
  2. 4 days
  3. 5 days
  4. 7 days
Q2 · medium · PYQ 2022
5 women can complete a work in 8 days, while 8 children take 10 days to complete the same work. How many days will 2 women and 4 children take to complete the work?
  1. 10
  2. 12
  3. 40
  4. 8
Q3 · medium · PYQ 2023
A tyre has two punctures. The first puncture along would have made the tyre flat in 9 minutes and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how long does it take both the punctures together to make it flat?
  1. 1\frac{1}{2} minutes
  2. 3\frac{1}{2} minutes
  3. 3\frac{3}{5} minutes
  4. 4\frac{1}{4} minutes
Q4 · medium · PYQ 2023
A sum of ₹ 25 was paid for a work which A can do in 32 days, B in 20 days, B and C in 12 days and D in 24 days. How much did C receive if all the four work together?
  1. ₹ 14/3
  2. ₹ 16/3
  3. ₹ 15/3
  4. ₹ 17/3
Q5 · medium · PYQ 2023
12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work?
  1. 10 days
  2. 12 days
  3. 15 days
  4. 9 days
💡 Want answers + explanations + 36+ more Time And Work questions? Sign up free →
⭐ Recommended for SSC GD aspirants

Full AI 6-Month

all your target exams · 6 months · unlimited mocks + AI
₹799~₹4.4/day
Sign up free, then unlockSee all plans →

More SSC GD topics

General Science
487+ practice questions
Geography
404+ practice questions
History
364+ practice questions
Polity
207+ practice questions
Antonyms
140+ practice questions
Synonyms
127+ practice questions

Free practice, AI explanations, 24 exams — all in one app

Daily 10-Q quiz · AI doubt solver in Hindi + English · adaptive mocks · 49,000+ practice questions (19,000+ verified PYQs).

Sign up freePricingTry Daily 10-Q