A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?

  1. A.10%
  2. B.(50/3)%
  3. C.20%✓ Correct
  4. D.25%

Explanation

Let the original number of men be M, completing the work in 6k days. Total work = M × 6k man-days. To complete the same work in 5k days, let the required number of men be M'. Then M' × 5k = M × 6k, so M' = (6/5)M = 1.2M. The increase is 0.2M, which is 20% of M. Hence the number of men should be increased by 20%.