A construction project was estimated to be completed in 180 days. Due to rain, only 60% of the days were productive. If the work done each productive day is constant, by what percent must daily output be increased to complete the project on time?

  1. A.70.43%
  2. B.66.67%✓ Correct
  3. C.60.65%
  4. D.65%

Explanation

Productive days = 0.6 × 180 = 108 days. To complete 180 days' work in 108 days, daily output must be 180/108 = 5/3 times. Increase = (5/3 − 1) × 100 = 66.67%.