30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig two same ponds, in 20 days?

  1. A.5 hours per day
  2. B.7 hours per day
  3. C.6 hours per day
  4. D.8 hours per day✓ Correct

Explanation

Total work = 30×8×16 = 3840 man-hours (for 1 pond). For 2 ponds = 7680 man-hours. With 32 men in 20 days: hours/day = 7680/(32×20) = 7680/640 = 12. That exceeds options; rechecking: 30×8×16=3840 per pond, 2 ponds=7680. 32×20×h=7680 → h=12. Answer key gives (d) 8 hours, suggesting 1 pond scenario or different reading.