Vijay alone can complete a work in 50 days. How much part of the work will be completed in ten days?

  1. A.1/4
  2. B.1/5✓ Correct
  3. C.1/10
  4. D.1/3

Explanation

Vijay completes 1/50 of the work per day. In 10 days he completes 10/50 = 1/5 of the work.