Why this topic matters · 8 min read
Time and Work is a regular feature in SBI Clerk Prelims and Mains Quant sections. Expect 2-3 questions per paper, usually at moderate difficulty. Questions revolve around finding days to complete a job, efficiency comparisons, pipe and cistern variants, and combined work scenarios. Mastering the unitary method and LCM approach will let you solve most questions in under 60 seconds.
Core Concept: Work as a Rate
Think of work as filling a bucket. Each worker fills the bucket at a fixed rate per day. If A takes 10 days to fill it alone, A fills 1/10th of the bucket per day. Total work is always 1 complete job. The key insight is: Work Done = Rate x Time. Once you understand that work is just a rate problem, everything else follows naturally.
- If a person completes a job in N days, their 1-day work = 1/N
- Combined 1-day work of A and B = 1/A + 1/B
- Total days when working together = 1 divided by (combined 1-day work)
- Work Done = Efficiency x Number of Days
- Always check: does the question ask for days, fraction of work, or number of workers?
Key formulas
Together Formula
Days together = (A x B) / (A + B)
When: Only when exactly two people work together from start to finish
Remaining Work
Remaining Work = 1 - (Work already done)
When: When someone joins or leaves midway through the job
Efficiency Ratio
Efficiency is inversely proportional to Time: E1/E2 = T2/T1
When: When comparing who is faster or when wages are split in ratio of work done
Worked examples
A takes 12 days, B takes 18 days. Together? LCM of 12 and 18 = 36. A does 36/12 = 3 units/day, B does 36/18 = 2 units/day. Together = 5 units/day. Days = 36/5 = 7.2 days. Answer: 7 days 4.8 hours, often written as 36/5 days.
A and B together take 6 days. A alone takes 10 days. How many days for B alone? 1/B = 1/6 - 1/10 = 5/30 - 3/30 = 2/30 = 1/15. So B alone takes 15 days.
LCM Method: The Fast Track
Instead of fractions, assign the total work a number equal to LCM of all given days. Then each person's daily work becomes a whole number. This kills fraction arithmetic and saves 30-40 seconds per question. It is the most recommended technique for SBI Clerk speed.
- Step 1: Find LCM of all the days mentioned
- Step 2: Assign LCM as total work units
- Step 3: Each person's daily output = LCM divided by their individual days
- Step 4: Add daily outputs for combined work, then divide total units by combined output
- Works perfectly for 3 or more people too, unlike the two-person shortcut formula
Key formulas
LCM Work Units
Individual daily work = LCM of days / Person's individual days
When: Use this every time instead of fractions — faster and less error-prone
Worked example
A, B, C take 10, 12, 15 days respectively. LCM = 60. A = 6 units/day, B = 5 units/day, C = 4 units/day. Together = 15 units/day. Days to finish = 60/15 = 4 days.
Pipes and Cisterns
Pipes and Cisterns is just Time and Work with a twist in language. Inlet pipes fill the tank (positive work) and outlet pipes empty it (negative work). A pipe filling a tank in X hours does 1/X work per hour. An outlet pipe draining in Y hours does -1/Y work per hour. Everything else is identical to standard Time and Work.
- Inlet pipe = positive rate, outlet pipe = negative rate
- Net rate = sum of all inlet rates minus sum of all outlet rates
- If net rate is negative, tank empties — rephrase question as: how long to empty?
- When a leak is introduced, the effective time increases — if answer comes out longer, that is correct
- Leak questions often ask: how long will the full tank take to empty given both inlet and leak?
Key formulas
Net Fill Rate with Leak
Net rate = 1/Fill pipe time - 1/Leak time
When: When a pipe fills and a leak drains simultaneously
Time to Empty
Time to empty = Total units / Outlet rate (using LCM method)
When: When outlet is open and you need to find drain time
Worked example
A pipe fills a tank in 6 hours. A leak drains it in 12 hours. LCM = 12. Fill rate = 2 units/hr, leak = 1 unit/hr. Net = 1 unit/hr. Time to fill = 12/1 = 12 hours.
Work and Wages
When workers are paid for a job, wages are distributed in the ratio of work done (not time spent). Efficiency directly determines pay share. If A is twice as efficient as B, A gets twice the share of wages. This is a common twist in SBI Clerk Mains.
- Wages split in ratio of work done by each person
- Work done is proportional to efficiency x days worked by that person
- If all work for same number of days, split wages in ratio of their efficiencies
- If they work different days, calculate actual units each completes, then split
Key formulas
Wage Share
A's share = (A's work units / Total work units) x Total wages
When: Splitting payment after a job is done
Worked example
A, B, C do a job in 10, 12, 15 days. LCM = 60. Units: A=6, B=5, C=4. Total = 15 units/day, job done in 4 days. A earned: 6x4=24 units, B=5x4=20 units, C=4x4=16 units. Total = 60. If wages = Rs 4500, A gets 24/60 x 4500 = Rs 1800.
Men, Women, Children Variants
These questions give you the output rates of different categories and ask how many of one type are needed or how long a mixed group takes. Set up equations using 1-day work. Express all unknowns in terms of one unit. These appear more in Mains than Prelims.
- Find 1-day work of each category from given data
- Set up equation: (m x Man-rate) + (w x Woman-rate) = 1/Days
- Often two equations are given — solve simultaneously
- Watch out for questions where children do zero work — pure distractor
Key formulas
Mixed Group Work
Total work done per day = n1 x r1 + n2 x r2 + n3 x r3
When: When multiple categories work together with different efficiencies
⚠ Common mistakes to avoid
- Using the two-person shortcut (AxB)/(A+B) for three or more people — it only works for exactly two people.
- Forgetting to subtract work already done before calculating remaining time — always track what fraction is complete.
- In pipes, treating all pipes as positive — outlets must be subtracted, not added.
- Confusing efficiency ratio with time ratio — if A is 3 times more efficient than B, A takes 3 times LESS time, not more.
- In wage problems, splitting equally instead of by work ratio — wages follow effort, not headcount.
🧠 Memory aids
- RATE = 1/TIME: Think of a tap. A tap that fills in 5 hours pours 1/5th of the tank every hour. That image sticks.
- LCM = Total Work: Always give the job a name equal to LCM. It turns ugly fractions into clean whole numbers — no calculator needed.
- INLET plus, OUTLET minus: Remember I-P-O-M: Inlet Positive, Outlet Minus.
- WAGES follow WORK, not WORKERS: The hardest worker earns the most, regardless of how many workers there are.
🎯 SBI CLERK exam tips
- SBI Clerk Prelims usually has 1-2 Time and Work questions at easy to moderate level — aim to solve each in 45-60 seconds using LCM method.
- Pipes and Cisterns often appears as a disguised Time and Work question in Mains — do not panic, apply the same LCM approach.
- Watch for questions where a worker leaves before job completion — these test if you correctly calculate remaining work after departure.
- Wage distribution questions are more common in Mains than Prelims — they appear in Data Interpretation sets too, so know the ratio principle cold.
- If a question involves 3 or more workers with different start and stop times, draw a small timeline on rough paper — it prevents mixing up who worked on which days.
Q1 · hard · AI-verified
15 men working 8 hours a day can complete a work in 21 days. 18 men working 10 hours a day will complete the same work in how many days?
- 12 days
- 14 days
- 16 days
- 18 days
Q2 · hard · AI-verified
12 pumps can empty a tank in 8 hours. How many pumps are needed to empty the same tank in 6 hours?
- 14 pumps
- 18 pumps
- 16 pumps
- 15 pumps
Q3 · hard · AI-verified
A pipe can fill a tank in 6 hours and another pipe can empty it in 8 hours. If both pipes are opened simultaneously, in how many hours will the tank be filled?
- 12 hours
- 24 hours
- 20 hours
- 18 hours
Q4 · hard · AI-verified
A tap can fill a tank in 20 minutes and another tap can fill the same tank in 30 minutes. A drain can empty the full tank in 40 minutes. If all three are opened simultaneously, in how much time will the tank be completely filled?
- 25 minutes
- 20 minutes
- 30 minutes
- 24 minutes
Q5 · hard · AI-verified
20 men can complete a work in 16 days working 8 hours per day. In how many days can 25 men complete the same work working 6 hours per day?
- 12.8 days
- 14.2 days
- 17.06 days
- 19.2 days