A and B can do a piece of work in 4 days. B and C can do the same work in 5 days, A and C can do it in 10 days. If A, B, C work together, in how many days can they complete the work?
A.11 7/3
B.3 7/11✓ Correct
C.3 11/7
D.11 3/7
Explanation
2(A+B+C) = 1/4+1/5+1/10 = 11/20, so A+B+C = 11/40. Time = 40/11 = 3 7/11 days.